Springville High Construction Updates
Overview as of February, 2025
Bid Pack #4 (the new Spring Acre Park) is out to bid.
All trades are ongoing.
The design for the new onsite tennis courts is complete.
Overview as of January, 2025
Masonry and building concrete are ongoing.
All trades are on track and ongoing.
Site concrete is being poured.
The plans for Bid Pack #4 (the new Spring Acre Park) will go out for bid on January 20th.
Overview as of December, 2024
Masonry and concrete are ongoing.
All trades are on track and ongoing.
Irrigation pumping system is installed.
Overview as of November, 2024
All on grade concrete has been poured.
70% of the second floor concrete has been poured.
Red Devil Drive asphalt is installed. The road is still closed to the public.
Overview as of October, 2024
The new Red Devil Drive is paved.
Masonry is ongoing.
Site is close to having on grade slabs poured.
Sod for the ball fields will be installed in early October.
Overview as of September, 2024
The floor in the auditorium is beginning to be poured.
Masonry is beginning in the gym.
Utilities on Red Devil Drive will be tied to 400 South.
The gas line for the new building is being installed.
Overview as of August, 2024
Bird Park- baseball and softball fields are progressing.
Concrete on site is at 80% complete.
Landscaping and turf are beginning.
The roundabout on Red Devil Drive is complete.
The new student parking lot is complete.
Overview as of July, 2024
All trades, except cabinetry, are working on the new building.
Dirt is continuing to be moved.
Pipes are being run.
The fences at Bird Park are being installed.
The announcer's booth have been painted.
Baseball field will be CLOSED until the project is complete.
The new parking lot and new Red Devil Drive roundabout will be completed by August 10th.
The roundabout will be under construction on Red Devil Drive throughout the summer. That road will be closed for the majority of the summer.
Overview as of June, 2024
Fencing is beginning to be installed around the baseball field.
Site concrete on the softball field is beginning.
Masonry for the dugout on the softball field is beginning.
Baseball field will be CLOSED until the project is complete.
The roundabout on Red Devil Drive will begin on June 10th and will be under construction throughout the summer.
Red Devil Drive will be closed for the majority of the summer.
The new parking lot and the new Red Devil Drive roundabout will be completed by August 10th.
There are two small parking lots that have been paved.
The school is progressing well.
Overview as of May, 2024
Grading is complete on the baseball and softball fields.
Landscaping around the fields is beginning this month.
Masonry and concrete slabs are continuing on the building site.
The roundabout will be under construction on Red Devil Drive throughout the summer.
Red Devil Drive will be closed for the majority of the summer.
SEE MAP BELOW FOR ALTERNATE ACCESS TO FIELDS.
Fields will remain in use until the season ends and then construction will begin.
Softball field: new field, new lighting, new backstops, new dugouts, and concession stand upgrade.
Baseball field: new dugouts, new backstops, and announcer booth upgrade.
Overview as of April, 2024
Underground irrigation piping is complete.
Red Devil Drive is underway.
Temporary power has been installed for the building.
Masonry, electrical, and concrete is still progressing.
The concrete footings for the gymnasium have begun.
Bird Park construction is beginning.
SEE MAP BELOW FOR ALTERNATE ACCESS TO FIELDS.
Fields will remain in use until the season ends and then construction will begin.
Softball field: new field, new lighting, new backstops, new dugouts, and concession stand upgrade.
Baseball field: new dugouts, new backstops, and announcer booth upgrade.
Overview as of March, 2024
The bidding process for Pack #3 is complete and pending approval from the Board.
The concrete pad is progressing.
Irrigation piping through Bird Park is beginning.
Masonry, concrete and electrical are all continuing.
Beginning to work with the city on preparing for the roadway on 400 South.
Bird Park construction will begin pending Board approval on March 13. SEE MAP BELOW FOR ALTERNATE ACCESS TO FIELDS.
Fields will remain in use until the season ends and then construction will begin.
Softball field: new field, new lighting, new backstops, new dugouts, and concession stand upgrade.
Baseball field: new dugouts, new backstops, and announcer booth upgrade.
***Red Devil Drive will be closed during Spring Break to install irrigation piping.***
Overview as of February, 2024
Underground site utilities are continuing to be installed.
40% of the concrete slabs have been poured.
Bird Park plans are out to bid and construction will be expected to begin in early March.
***Red Devil Drive will be closed during Spring Break to install irrigation piping.***
Overview as of January, 2024
Beginning masonry.
Construction pad is 100% complete.
Irrigation piping is 75% complete.
Footings and floors are continuing to be poured.
Coordination with Springville City on Bird Park plans (Bld Pack #3) are being finalized.
The school is approximately 17% complete.
Overview as of December, 2023
Irrigation piping is underway- 30% complete.
Beginning stages of pouring floors.
Bid for Bird Park- baseball and softball fields- will be going out in February.
The school is approximately 10% complete.