Springville High Construction Updates

Construction Site Map

Overview as of February, 2025

  • Bid Pack #4 (the new Spring Acre Park) is out to bid.

  • All trades are ongoing.

  • The design for the new onsite tennis courts is complete.

Overview as of January, 2025

  • Masonry and building concrete are ongoing.

  • All trades are on track and ongoing.

  • Site concrete is being poured.

  • The plans for Bid Pack #4 (the new Spring Acre Park) will go out for bid on January 20th.

Overview as of December, 2024

  • Masonry and concrete are ongoing.

  • All trades are on track and ongoing.

  • Irrigation pumping system is installed.

Overview as of November, 2024

  • All on grade concrete has been poured.

  • 70% of the second floor concrete has been poured.

  • Red Devil Drive asphalt is installed. The road is still closed to the public.

Overview as of October, 2024

  • The new Red Devil Drive is paved.

  • Masonry is ongoing.

  • Site is close to having on grade slabs poured.

  • Sod for the ball fields will be installed in early October.

Overview as of September, 2024

  • The floor in the auditorium is beginning to be poured.

  • Masonry is beginning in the gym.

  • Utilities on Red Devil Drive will be tied to 400 South.

  • The gas line for the new building is being installed.

Overview as of August, 2024

  • Bird Park- baseball and softball fields are progressing.

    • Concrete on site is at 80% complete.

    • Landscaping and turf are beginning.

  • The roundabout on Red Devil Drive is complete.

  • The new student parking lot is complete.

Overview as of July, 2024

  • All trades, except cabinetry, are working on the new building.

  • Dirt is continuing to be moved.

  • Pipes are being run.

  • The fences at Bird Park are being installed.

  • The announcer's booth have been painted.

  • Baseball field will be CLOSED until the project is complete.

  • The new parking lot and new Red Devil Drive roundabout will be completed by August 10th.

  • The roundabout will be under construction on Red Devil Drive throughout the summer. That road will be closed for the majority of the summer.

Overview as of June, 2024

  • Fencing is beginning to be installed around the baseball field.

  • Site concrete on the softball field is beginning.

  • Masonry for the dugout on the softball field is beginning. 

  • Baseball field will be CLOSED until the project is complete.

  • The roundabout on Red Devil Drive will begin on June 10th and will be under construction throughout the summer. 

  • Red Devil Drive will be closed for the majority of the summer.

  • The new parking lot and the new Red Devil Drive roundabout will be completed by August 10th.

  • There are two small parking lots that have been paved.

  • The school is progressing well.

Overview as of May, 2024

  • Grading is complete on the baseball and softball fields.

  • Landscaping around the fields is beginning this month.

  • Masonry and concrete slabs are continuing on the building site.

  • The roundabout will be under construction on Red Devil Drive throughout the summer.

  • Red Devil Drive will be closed for the majority of the summer.

  • SEE MAP BELOW FOR ALTERNATE ACCESS TO FIELDS.

    • Fields will remain in use until the season ends and then construction will begin.

    • Softball field: new field, new lighting, new backstops, new dugouts, and concession stand upgrade.

    • Baseball field: new dugouts, new backstops, and announcer booth upgrade.

Overview as of April, 2024

  • Underground irrigation piping is complete.

  • Red Devil Drive is underway.

  • Temporary power has been installed for the building.

  • Masonry, electrical, and concrete is still progressing.

  • The concrete footings for the gymnasium have begun.

  • Bird Park construction is beginning.

    • SEE MAP BELOW FOR ALTERNATE ACCESS TO FIELDS.

      • Fields will remain in use until the season ends and then construction will begin.

      • Softball field: new field, new lighting, new backstops, new dugouts, and concession stand upgrade.

      • Baseball field: new dugouts, new backstops, and announcer booth upgrade.

Overview as of March, 2024

  • The bidding process for Pack #3 is complete and pending approval from the Board.

  • The concrete pad is progressing.

  • Irrigation piping through Bird Park is beginning.

  • Masonry, concrete and electrical are all continuing.

  • Beginning to work with the city on preparing for the roadway on 400 South.

  • Bird Park construction will begin pending Board approval on March 13. SEE MAP BELOW FOR ALTERNATE ACCESS TO FIELDS.

    • Fields will remain in use until the season ends and then construction will begin.

    • Softball field: new field, new lighting, new backstops, new dugouts, and concession stand upgrade.

    • Baseball field: new dugouts, new backstops, and announcer booth upgrade.

  • ***Red Devil Drive will be closed during Spring Break to install irrigation piping.***

Overview as of February, 2024

  • Underground site utilities are continuing to be installed.

  • 40% of the concrete slabs have been poured.

  • Bird Park plans are out to bid and construction will be expected to begin in early March.

  • ***Red Devil Drive will be closed during Spring Break to install irrigation piping.***

Overview as of January, 2024

  • Beginning masonry.

  • Construction pad is 100% complete.

  • Irrigation piping is 75% complete.

  • Footings and floors are continuing to be poured.

  • Coordination with Springville City on Bird Park plans (Bld Pack #3) are being finalized.

  • The school is approximately 17% complete.

Overview as of December, 2023

  • Irrigation piping is underway- 30% complete.

  • Beginning stages of pouring floors. 

  • Bid for Bird Park- baseball and softball fields- will be going out in February.

  • The school is approximately 10% complete.